plaster cake: before wall pasting, the base layer needs to be laid with ash, according to the verticality and flatness of the wall, with slightly dry mortar on the wall according to the position of the control point to make plastering control points and surfaces, the wall must be done at both ends, the distance between 1.5M or so. It

plastering the bottom layer: plastering the bottom layer of ash generally divided into two operations, first brushing a plain cement slurry adhesive layer, and then immediately followed by plastering the first side of 1:2.5 or 1:3 cement mortar, requires a thin layer and plaster compaction. The second time with the same mix of mortar punch and plaster flat, scraped with short bars, low concave filling, and finally rubbed out with a wooden plaster hemp surface. According to weather conditions, after final solidification, watering maintenance.